Showing posts with label Peat. Show all posts
Showing posts with label Peat. Show all posts

Wednesday, 29 March 2017

The Impact of High Levels of Wind Energy on Conventional Plant

On Wednesday 25th January 2017 wind energy reached a new record of 2,400MW for the Republic of Ireland. This post will look at the impacts on some of the other generation sources.


CCGT ( Gas)




Only three out of eight CCGT ran during the day - two in Dublin (Poolbeg and Dublin Bay) and one in Cork (Whitegate). Presumably, the other 5 plants were paid capacity or constraint payments to shut down for the day.

Wind generation was unusually stable during the day and so Dublin Bay and Whitegate mostly followed demand while the output from Poolbeg had a flat profile. Dublin Bay ran the most efficiently. Whitegate's output hovered between 45% and 60% of it's maximum (or rated capacity otherwise known as load). Poolbeg, on the other hand, operated at about a quarter of it's rated capacity. Operating a CCGT at this level leads to higher specific emissions and fuel consumption, something like driving your car in second gear all the time. 

It would have been therefore preferable to have operated Whitegate on higher loads and take Poolbeg off the grid altogether. The requirement for two power stations to be on load at all times in the Dublin area probably lead to this less than ideal situation.


Coal 




Two out of the the three generators at Moneypoint operated for the day and like the CCGT mostly followed demand.   They operated at an average of 50% of maximum output with minimum output at 40%. A load of 40% capacity is likewise not exactly ideal in terms of efficiency. 


Peat





The three peat power stations are being run on baseload and as a result are not affected by high wind levels. The biomass component seemed to be out of action. The question arises as to why (like wind) peat still receives a subsidy if it is always allowed to operate in the electricity generation market (Though I think the peat subsidy is being phased out). 


OCGT (Gas)




Both open gas cycle units at Sealrock operated at close to full output for the day as like wind they have priority dispatch in the system.


Demand Side Units (DSU)




One relatively new problem for Eirgrid is that despite having all this additional generating capacity in place, matching supply with demand is not as straightforward as previously thanks to the presence of stochastic wind energy. Fast acting plant is one answer to this. Another solution is reducing demand during periods of high demand. Demand side units reduce the demand during peak times giving industrial users a choice to shut down production or use their own diesel generators. 

As more wind is added, more reliance will be placed on DSUs and ironically diesel generation. During this day, on average 18MW per hour of DSU was called on to help keep the lights on. Not a significant amount at this stage. But according to Eirgrid :


The capacity of Demand Side Units in Ireland has increased to 230 MW, and is set to increase further. 


East West Interconnector to UK (EWIC)

The UK interconnector played a crucial role on this day. For most of the time, Ireland sent across it's surplus wind but for an hour, between 6pm and 7pm, Irish generation was insufficient to meet the rise in demand as people arrived home from work and turned their kettles and cookers on. It's an unfortunate fact that you can't "switch the wind on". Also you can't simply switch a large power station like a CCGT on. 

The preferred solution by Eirgrid, presumably because it was cheaper than the other option discussed below, was to reverse the direction of electricity in the interconnector. However, the UK was strapped for generation at this time and (incredibly) France were reliant on UK imports. A precarious situation for the UK but 120MW of spare power for Ireland is not a significant amount for a system of their size.




There is still a shortfall of about 200MW at peak time (where blue line is higher than orange line in the second graph above) which I'm not sure how they made up. Possibly more hydro or DSU or some other peaking plant that I may have missed.

The other option available to Eirgrid would have been to simply increase output from Poolbeg as the demand began to rise. After all, it was being operated at well below optimum efficiency as discussed above.  This is presumably what would have happened if there was no interconnector. Usually the low cost of power purchased from UK would make importing a cheaper option but I can't imagine a grid with such a tight capacity margin as the UK's giving away low cost power during peak demand times. But I can only assume it was somehow cheaper in this case.


The power UK sent to Ireland was made up mainly of gas and coal generation with some nuclear and wind : 




The generation mix for the day is given below  :




Tuesday, 26 January 2016

Power from Peat : A Lesson from the Past


100 years ago, energy experts advised us that we could reduce dependence on imported coal by using our own peat to power industry. Germany and Denmark were held up as examples to follow for Ireland. Sound familiar ? Peat, notwithstanding the environmental impact on bogs from it's large scale extraction, is one of the most polluting sources of fuel and Ireland is still using it as a power generation source today (although the subsidy is to phased out). We can now see that the energy experts got it really wrong. The claims they made at the time are reminiscent of claims been made now by green energy advocates. 



Newspaper article from 1916

Before we begin harvesting our own fuel sources, proper analysis needs to be carried out. Peat generation eventually needed a subsidy to remain profitable. Coal generation never required a subsidy.

We now have technical and environmental assessments that carry legal standing to ensure this doesn't happen again. Why aren't we doing them ?

Saturday, 21 March 2015

What's In Your Electricity Bill: Part 5 - The PSO Levy

PSO Levy could increase by € 550 million by 2020


The PSO Levy is possibly one of the craziest schemes ever introduced by an Irish Government (along with electronic voting machines, bank guarantee etc). While the idea is to promote fuel from indigenous sources, the result is bad for competition and bad for the consumer. The levy reimburses generating companies when the wholesale prices are low. It props up peat and wind plants aswell as some idle gas plants. You could be fooled for thinking that the substantial capacity payments already been paid to these plant was for this very purpose, but nothing about the electricity market in Ireland is straightforward.

Imagine if the price of bread was suddenly cut in half but the government slapped a levy on the bread to bring the price back up to normal levels. But instead of the levy going to the government, as happens with petrol, it goes back to the bakery. This would result in a win-win situation for the baking companies and a lose-lose situation for consumers. In effect, it acts as a buffer against market forces. Yet we were told by Minister Dempsey in 2007 that "we are introducing structural changes in the electricity sector that will create a more attractive investment climate for existing and new players, deliver increased competition, reduce the cost of electricity and offer greater choice for consumers”. But in 2010, instead of enjoying the fruits of a competitive electricity market, consumers began paying the PSO Levy which ensured energy companies made profits on certain generators regardless of what happened to prices in the market (Note 1).

It's true that only a portion of the levy goes to wind generation. But a closer look is required to see what is going on.

This chart shows where the PSO Levy goes :



Gas generation


The single biggest beneficiary of the PSO Levy is Tynagh gas plant whose profits soared to €40 million in 2013 :

http://www.irishtimes.com/business/energy-and-resources/tynagh-energy-profit-soars-60-to-40m-after-shutdown-1.2037578

Tynagh is not run very often but cannot be allowed to close down as this could affect "security of supply" - in otherwords, when the weather does not deliver in terms of wind energy, the good old reliable fossil fuel plant will step in. Lower demand is also a factor because this means the plant receives less income from the market. Tynagh will receive €69 million from the PSO this year - about 21% of the total levy. The Energy Regulator explains :

 This is because most of Tynagh’s allowed PSO costs are fixed rather than related to its output, so the less the plant runs and receives correspondingly lower SEM revenue, the higher the PSO subsidy needed to cover its allowed fixed costs.


But as we can see above, Tynagh does not just recover its fixed costs, it makes substantial profits from the PSO.

Aughinish and Tynagh entered a contract for differences (CfD) agreement with Electric Ireland, whereby EIectric Ireland recovers or returns additional monies paid under the agreement from/to the PSO levy. These arrangements were put in place for a 10 year period, and are accordingly expected to end in 2016, at which
point they will no longer receive ex-ante PSO payments.

It will be interesting to see if the PSO Levy will be extended next year for Tynagh but for the purposes of this blog I will assume that it will extended. Indeed, in Eirgrids recent capacity statement, on page 51, you can see that the plant is expected to remain open up to (at least) 2024.

Peat generation


Peat receives the largest proportion of the levy at 35% but there are no new peat plants in planning. So we can assume that this charge will remain roughly static in the coming years. There will come a time when these peat plants will have to be closed down and replaced as the fuel runs out. Bord Na Mona, the semi state company that runs these plants have now diversified into wind energy. But as wind energy (non dispatch) is incapable of replacing dispatchable peat generation, there will still be a gap in the power generation supply market of about 340MW when the peat plants close down that will have to be met by something else e.g. biomass or gas.

Eirgrid expect the 3 peat plants to still be in operation up to 2024 at least.

Wind generation


Wind energy is given a fixed price plus 15% for electricity generated called REFIT (Renewable Energy Feed In Tariff, it works out at around €80 MWh compared to €43 MWh for gas). The PSO levy finances REFIT by making up the shortfall wind receives from the market.

Wind makes up 27% of the levy but this is one to watch as 1,000's of new MWs are planned. I have seen various reports of the amount of planned wind farms ranging from 4,000MW to 6,000MW and even more than that. But Eirgrid seem to think around 4,000MW is required to meet the targets. So that means that about 2,000MW more is due to be built by 2020. So how much will this cost the consumer in terms of PSO Levy ?

Let's look at this step by step :

  1. The allowance for REFIT increased from € 51.07 million to € 90.5 million this year. This is a hike of € 39.43 million.
  2. We are told that "Overall the amount of renewable generation, mostly wind, estimated to receive the PSO levy next year is 138 MW more than the current year (due to REFIT 2 primarily), hence increasing the levy". So we will be building approx 14 times more than this amount by 2020 (138 x 14 = 1,932MW).
  3. So 138MW of new wind generation requires € 39.43 million from PSO. We are building 14 times this capacity between now and 2020. Multiplying 14 by € 39.43 million gives us € 552 million additional PSO required for wind (39.43m x 14 = 552m).

So we will have to increase the PSO Levy by € 552 million to pay for all this additional wind. So who will pay for this ? Well page 32 of the PSO Levy Decision Paper shows how much extra each consumer type pays for the current PSO increase.  So we can deduce from that how much the € 552 million will cost for each consumer type (Note 2) : 


+ 2,000MW wind = + € 552 million PSO by 2020 paid for by :


Domestic customers  = + € 300 per customer per year
Small commercial customers = + € 1,285 per customer per year
Medium/large customers = + € 220 per kVA

As you can see a €300 increase will drive many families into fuel poverty. As for SME's, a near 
€ 1,300 hike in their bills will put a lot of them out of business. Large industry will simply look elsewhere to locate their plant - Poland, USA, India or perhaps China. 

It will be argued that this increase will be offset by savings due to more wind generation. But there are more system costs due to more wind apart from the PSO Levy as the Energy Regulator recently pointed out  :


So it's hard to see much savings, if any, from adding more wind at this stage. 

Our government has locked society into high electricity bills for many many years to come. The combined social impact of this along with the other charges recently introduced for water etc and carbon taxes will change the lives of many Irish families whose lives revolve around access to relatively affordable electricity. 

Disconnections will bring home to many people the true nature of the energy policy devised by the previous government.  But by then, like the banking collapse of 2008, it will be too late. 

_________________________________________________________________________________

Note 1

Noel Dempsey (Fianna Fail) was Minister for Energy from September 2004 till June 2007. He was succeeded by current Green Party leader Eamon Ryan who held the position until January 2011. So the question as to what happened between the time Noel Dempsey brought in the "structural changes" and Eamon Ryan's tenure ended could be the topic of another article or indeed a book to do it full justice.

Note 2

Workings based on information provided in CER PSO Levy Decision Paper 2014/15 - page 32

https://www.cer.ie/docs/000967/CER14361%20PSO%20Levy%20Decision%20Paper%20%202014-15%20%28New%29.pdf

14 is the multiple of wind generation required to get to 4,000MW as per Step 2 above.

Domestic : €42.87  - €64.37 = €21.50 increase this year. 
€21.50 * 14 = € 301 per customer per year

Small commercial customers : €129.83 - €221.66 = €91.83 increase this year. 
€91.83 * 14 = € 1,285 per customer per year

Medium and large customers : €18.47 - €34.20 = €15.73 increase this year. 
€15.73 * 14 = € 220.22 per kVA