The North South Interconnector - what is the payback of the project ?
The North South Interconnector is hailed as the panacea to Northern Ireland's electricity woes.
If we
consider Eirgrid’s figures for the interconnector for 2020, they claim a central estimate of €20
million for 2020 and a sensitivity estimate of €13 million. The latter one is
actually the justifiable figure. So how much does the North South
Interconnector cost? In the presentation to the
Oireachtas Committee of 16
th
June 2015,
it was clarified by Jenny Pyper, who is the Chief Executive of the Utility
Regulator in Northern Ireland:
- I should apologise for the absence of a crucial bullet point which
provides the total project cost of the North-South interconnector,
including overhead line, land acquisition, substation and other costs. The
total project cost is €286 million
- It is important to understand that, while the security of supply
concerns do not directly apply to us - we probably have more comfort in
the Republic in terms of the capacity available for generation - there is
an argument that we have an excess that cannot flow to Northern Ireland
because the second interconnector is not available at the moment, which is
imposing costs on consumers. This extra cost, which we think at minimum is
about €10 million per annum, is the primary concern from the Republic's
point of view.
Note: None of this
includes the cost of the 600 MW of wind energy in Northern Ireland to be
facilitated by the North South Interconnector, which as previous is in the order
of €2 million per MW installed capacity.
From an engineering
perspective what is provided above is simply astounding, a project cost of €286
million and a realist return of €13 million results in a simple payback of some
22 years. In the private sector a project would need a simple payback of some 5
years before it would be considered as viable. As regards the actual payback,
then one has to include other costs, such as maintenance, operational costs,
depreciation, interest rates on borrowings, etc. So this would push the 22
years out by many more. It is generally recognised that the economic lifespan
of high voltage transmission systems is 45 to 50 years, so the payback on this
proposed North South Interconnector project would be in the order of half its
expected lifespan. In engineering terms this is simply absurd.
For instance, if we
consider the UK’s Department of Energy & Climate Change report on “Research
to Assess the Barriers and Drivers to Energy Efficiency in Small and Medium
Sized Enterprises”, then this clarified with respect to payback period:
- The majority of Interviewed Businesses reported that energy
efficiency improvements with a payback period of less than two years made
business sense and would be likely to go ahead if finance was available;
some extended this to five years.
Why is this so,
because it reaches a point where there are simply far better opportunities available
to achieve an actual return on the investment, i.e. there is a better bang for
the buck elsewhere. After all nobody begrudges that public money is spent on
essential infrastructure for health and education, but what is proposed is a
project, which wouldn’t see the light of day in the private sector, due to its
chronic lack of viable payback. Have Eirgrid looked at alternatives properly ?
As was highlighted in Part 1, Northern Ireland requires new dispatchable generation
capacity to replace that which no longer meets EU emissions standards. Could
such capacity be installed for the reported €286 million, which is to be spent
on the North South Interconnector plus the €2 million per MW to be spent on the
associated 600 MW of wind energy? Given that the installed cost of Combined
Cycle Gas Turbine technology
is less than €0.9 million per MW,
then the overwhelming answer is yes it could. So why was this option not
investigated in the consideration of alternatives by Eirgrid?