Showing posts with label Peak Demand. Show all posts
Showing posts with label Peak Demand. Show all posts

Wednesday, 24 November 2021

Peak Winter Demand Arrives

Things get a little bit shaky !

 Last night at 5.30pm, the electricity grid hit peak demand for All Ireland at 6,638MW - not far off Record peak demand of 6,878MW reached on December 21st last year.



.

But total system generation was only 6,106MW leaving a shortfall of 532MW.  


Wind energy was low most of the day, only 380MW or about 7% was available for the whole island at 5.30pm.



The two UK interconnectors saved the day with combined imports of 450MW. There was still a shortfall of about 80MW, made up presumably from demand side units. These would comprise mostly of diesel generators and combined heat and power units. These units are "non-centrally monitored" according to Eirgrid and are not included in these graphs.  



Of course, that damned Brexit lot across the sea with their dastardly nuclear power charged us handsomely for the imported power, at € 2,000 a MW. 




To give some credit to the Irish grid operators, they were correct to build the East West interconnector as it is making up for the once efficient gas plant that have been prematurely wrecked from backing up the wind. One just hopes that the UK will have sufficient power to give us on those cold winter nights over the next few months. 






Thursday, 30 September 2021

How Close is Ireland to Blackouts ?

 

                                  Chart 1 - The green line includes all potentially available capacity whether currently in use or not. Some adjustments have been made to the red line to take account of the temporary loss of two gas and one oil generators . 


The above graph shows how Ireland's electricity supply position has evolved since the height of the building boom in 2006. The green line shows the total generation capacity that consumers must pay for including wind energy. As you can see the gap between the green line and peak demand in blue has increased exponentially in tandem with the building of new wind farms in yellow and new power stations in red. This gap is a large part of the reason why electricity bills have soared in recent years as the capital element of all of this capacity must be financed through bills regardless of how much energy they produce. So with all of this excess capacity, how is it that we are facing the prospect of blackouts? 

The red line is dispatchable plant, that is, plant that can be switched on at a moment's notice as required. The main ones in Ireland are gas, coal and oil power stations. The interconnector to England (EWIC) is also included in this however it's debatable how dispatchable this is in light of recent events (more on this later). Peat is also dispatchable but two of those power stations were closed down in 2020 leaving only one remaining peat station in Edenderry which also runs on biomass. It is due to be closed down in 2023. It has now finally being accepted by almost everyone (apart from the Green Party Energy Minister ?) that wind is not dispatchable and during long periods of low wind as we have had this year it is really the red line that we are relying on to keep the lights on.

The red line takes a noticeable dip after 2020. This is to take account of the loss of three power stations during 2021 - Huntstown 400MW, Whitegate 444MW and Tarbert 243MW. This has returned us to 2007 levels of dispatchable plant. This shouldn't present a serious problem, we managed okay back then. However, there are two main differences between now and back in the Tiger days :

1) Peak demand has increased by about 10%. The peak of 5,357MW was reached in December 2020. It is likely that this will increase further this winter which means the gap between the red and the blue line in Chart 1 will narrow even further. 

2) The rate of forced outages has increased dramatically in recent years. According to Eirgrid, the forced outage rate went from a low of about 3% in 2016 to a high of about 16% in 2021. The forced outage rate is the rate at which power stations are breaking down. Power stations are becoming less reliable and not just old ones. One reason for this is that they are switching on and off too much to balance the wind (more here) . 

The situation then is precarious enough but what happens if the UK does not have spare energy to give to us over the interconnector ? This has become a greater risk as energy shortages have recently become a major political issue in the UK. Chart 2 shows what happens when the EWIC is no longer available :



Chart 2


There is now a very small gap between the red and blue lines. 353MW to be exact. Which is about the size of a single power station. So another power station outage would leave us on the precipice and if the winter is a cold one demand will surely rise pushing us over the edge into blackout territory. 

To sum up here, it would take six events occurring at the same time to leave us in a very dangerous position - three of those are the three currently unavailable power stations not being repaired in time for winter, the fourth is the interconnector becoming useless, the fifth is either another power station breaking down or demand rising higher than last year. The trend for the fourth and fifth events is going the wrong way in all cases. The likelihood however of all 3 power stations not being repaired in time for winter is fairly slim although I have a feeling Whitegate may not be repaired by mid November as scheduled.

The sixth event is perhaps the biggest variable of all, the yellow line in the charts - wind energy. If there is plenty of it then in theory the majority of these events occurring simultaneously would not pose such a major problem. But if we have another lull as we have had this summer then that is a different story.

I say, in theory, because it is slightly more complicated than that. Certain power stations are required to be operating at all times to maintain the stability of the grid. Currently that includes Moneypoint coal power station. Moneypoint happens to be the oldest power station on the grid so there is a risk to the entire grid if it alone suffers an outage. No amount of wind energy can replace the inertia that Moneypoint provides to the system. 

In any event, the demand of large energy users will most likely be cut before we get near the precarious position of all or most of these events occurring together. 

Demand management they are calling it. Which is another form of blackout, just with a nicer name . 


Saturday, 18 September 2021

Record Prices hit the Irish Electricity Market

 On Thursday the 9th September, prices in the All Ireland Electricity Market hit record highs of €4,680 per MWh, well over 20 times the normal price :


The scale here is from €0 to €5,000 MWh


What a normal day looks like, prices rise to about €150 MWh


These prices may have had something to do with the UK switching on coal plant that same week, the cost of which can be very high. Margins are set to get even tighter in the UK as this week one of the interconnectors to France went on fire causing wholesale prices to rise even higher there. Low outputs of wind energy have plagued both Ireland and the UK for many months now. In essence, high prices in the electricity market go hand in hand with low amounts of reliable generation.

There have been three Amber Alerts and seven Notifications of Tight Generation Margins issued this month in the Single Electricity Market (SEM). An Amber Alert means there was expected to be enough energy to meet demand, but possibly not enough in reserve should something go wrong. They can also be issued if there are significant frequency / voltage deviations which can happen when there aren't enough large power stations on the grid. The notification of Tight Generation Margins seems to be a prelude to an Amber Alert. 

System Alerts can go from Alert (Amber) to Emergency (Red) to Blackout (Blue) and finally to a Restoration state. Up to the end of August of this year there have been six system alerts on the grid. In the previous decade, they averaged just one per year.








Tuesday, 15 December 2020

Amber Alert With More Generation ?

 Eirgrid warned this week of an Amber Alert due to high peak demand, a loss of a number of generators and low wind generation :

“There were a number of reasons that gave rise to Wednesday’s alert. Firstly, two of the three units at Moneypoint, the country’s largest power station, suffered technical failures and were not available. This resulted in the loss of 570 megawatts of electricity.

“Generation at Whitegate power station in Cork totalling 450 megawatts was also unavailable due to technical issues. A 243 megawatt generator at Tarbert power station was called up but could not respond due to technical problems. 

“The electricity market was set up for Ireland to export renewable energy via the two interconnectors (EWIC in the South and Moyle in the North) linking Ireland and GB.

“Following the issuing of the amber alert we were able to reverse the flows on the Moyle Interconnector and on EWIC shortly after that. There was also a drop in wind generation greater than was forecast prior to the alert being issued.

“There was no loss of electricity during the alert which ended by 6.20pm on [Wednesday],” the spokesman explained.


 Apparently the last time we hit such a demand was back in 2010 but there was no mention of an alert back then. In 2010 there was 1,405MW of wind installed on the grid. In 2019 this reached 4,235MW (+2.8 GW). The 500MW EWIC interconnector was commissioned in 2012. 

So the question has to be asked, how is it that with 3.3GW of additional generation equipment, we are now struggling to meet demand? 


 

Saturday, 12 December 2020

Have A Green Green Christmas !

 Blackouts on the Way ?

Val Martin reports on what we predicted many years ago would happen as unreliable wind energy became a major energy source in the grid:



There are a number of unusual events occurring at the same time this winter :

  • On the 10th December, peak demand exceeded that of 2010:


  • Two peat power stations have been closed down by the Greens, a loss of 228MW
  • Whitegate power station is offline due to a forced outage, a loss of 440MW
  • Indaver waste to energy plant is offline due to a forced outage, a loss of 17MW
  • The forced outage rates has increased every year for the past four years, which tends to support the theory that higher levels of wind energy leads to excessive cycling and ramping of generators which they were not designed for.
  • Increased reliance on UK interconnectors, a country that has trouble itself with keeping the lights on.
  • the all-island winter capacity margin has reduced every year over the past five years mainly due to increasing demand, dispatchable generation exiting the market and increasing generator forced outage rates. The capacity margin is the spare capacity available to meet peak demand. It is now at its lowest in recent times :



Source: Eirgrid Winter Outook




Monday, 4 May 2020

Fuel Consumption 2012 to 2018 - the Good, the Bad, and the Ugly


In the course of the transition we will gradually reduce our dependence on the fossil fuels – coal, peat, oil and gas – that currently dominate our energy mix - Alex White, Energy Minister, White Paper, 2015


Despite massive efforts to reduce carbon emissions and fossil fuel dependence by successive Irish governments, the efforts have largely proven a failure, as fossil fuel consumption rose by 15% between 2012 and 2018. The government placed an overemphasis on wind energy as the solution, which doubled in capacity during that time to 3,600MW. Demand may also have increased, which in of itself is a failure to reduce consumption habits, and an over emphasis on the generating of electricity. Demand could have been tackled through retrofitting, promotion campaigns aimed at reducing consumption, moving away from the GDP standard, encouraging saving rather than spending (central bank have been doing the opposite), and preventing population growth by curbing immigration.

The main driver of the increase was petroleum products, including natural gas (used in power stations), which has risen by about 20%.



Natural Gas increased by 20%
In 2012, gas generated half of our electricity, as it did again in 2018, but this time with a significantly higher gas consumption. When your car comes off the motorway and goes into ‘stop start’ urban driving it burns more fuel, just like power plants forced into such operation, as intermittent wind energy pours on and off the grid.   


In their favor, coal and peat decreased by 23% and 8% respectively. The reduction in these, contrary to the common held belief, was due to several factors  - an increase in gas, oil, renewables and electricity imports from the UK (the East West Interconnector began operation in late 2012).  The US achieved a 27% reduction in CO2 emissions during the period 2008 to 2017 by simply switching from coal to gas. So too emissions savings in Ireland arise from switching from coal to gas, a lower emitting fuel,  and importing electricity from the UK, where the resulting emissions are counted, and after that, renewables make up the rest of the savings.  





Peat decreased by 8%



For gasoil and diesel we can see that not only has dependence on transport risen, but  oil used in power generation has also, quite remarkably, increased. Much of this increase is due to an oil powered station in Kerry (Tarbert) which ran more in the grid, presumably because of the closures at Moneypoint. There are also more demand side units, which comprise of diesel generators.



We can also see that we are more addicted to air travel than ever, as jet kerosene consumption doubles. How could a virus pandemic ever be prevented from reaching our shores ?

So we have to ask the question, why are we still consuming high amounts of fossil fuels, after installing so many wind turbines ?  Media reports that show that a high percentage of our electricity came from wind fail to mention what we actually saved as a result. If I cycle from Dublin to Galway, but a car follows me all the way, what have I actually saved ? It is obvious now that they are not a long term solution to reducing dependence on fossil fuels. 

In 2020, there is still, regrettably, peat being used in electricity production, although there is an issue about the impact on employment in the midlands region that has still not being resolved. The renewables industry, as we now know, is not a big employer. 

The Energy Bubble


Generating Capacity for the Republic of Ireland, we have over twice as much as we need

The above graph shows how an energy bubble has been created in the past decade. Whereas in 2006, at the height of the building boom, we only needed enough generating capacity to cover 1.3 times the peak demand, we now have 2.4 times the capacity required. Peak demand levels in 2019 are the same as 2006 levels. All this capacity has to be paid for either through the market or from subsidies that are added on to energy bills. New fossil fuel plant are also in the pipeline.

The Cost 


The EU publishes an energy price report every two years. The last year available of full data is 2016; which shows a circa €490 billion bill for energy sources, €212 billion being imported fossil fuels, plus an additional tax squeeze of €280 billion, of which €76 billion in subsidies is for the renewable sector equating to €208 million per day or €150 from each citizen.

€48 billion was paid directly to wind and solar generators on top of the market price for generating 13% of EU’s electricity mix. 

The market price plus tax paid to gas and solid fuel generators, for generating 41% of the EU's electricity mix, were also €48 billion. 

Turkeys would not vote for Christmas if they were able to educate themselves.


Monday, 16 October 2017

Data Centres Vs Steel Plants - A Comparison

SUMMARY

•  Steel plants use 60% of the energy demand of a data centre but provide 26 times as many jobs

• Port Talbot steel plant in Wales provides 28.5 jobs for every megawatt of demand compared to 1.5 at the data centre at Athenry 

• Approval for planning permission of any industrial project should require a high jobs to energy demand ratio of at least say six or seven. 


Last week, Apple received approval for their data centre in Athenry, County Galway to great fanfare in the media. I can only find one article (in the Independent) which dealt with facts (Revealed: Data centres to swallow 75pc of growth in Irish power demand). The article gives a good overview of the problems that lie ahead. 

I am not in favor of opposing something for the sake of opposing it. I'm in favor of discussing all the available facts and basing decisions on those. What we have now in Ireland is approving something for the sake of approving it which is just as bad as the other extreme.  I fail to understand how a country which prides itself on it's higher education credentials does not discuss the facts in relation to new projects such as data centres. 


David Hughes wrote previously on the Athenry data centre (The Cloud Bytes Back) :

To give an example Apple are seeking permission for a 240MW data centre in Athenry Co. Galway, which will create up to 215 jobs. The electricity consumption of this data centre will be the same as 420,000 Irish homes. This is ¼ of all Irish homes or every single house in Dublin City, Dun Laoghaire, Fingal and South County Dublin combined. Basically, the electricity needs of 1 Million people.
It seems the jobs figure has been revised downwards to 150 full time jobs according to the above Independent article.  So that's about 1.5 jobs for every megawatt of demand.  

Let's compare that to another high energy industrial user - steel plants in the UK. Port Talbot steel plant in Wales was due to shut down in the near future but the employees fought hard and the plant remains open for the time being. It employs nearly 4,000 people.


Port Talbot steelworks’ current demand for energy is about 140 Megawatts (MW), about half of which is internally generated. That works out at 28.5 jobs for every megawatt of demand.


A steel plant therefore generates about eighteen times more jobs per megawatt of demand than a data centre. Even if those jobs were cut in half by new technology, steel would still provide more jobs by a factor of nine.


Based on figures for Port Talbot then, steel plants use 60% of the energy demand of a data centre but provide 26 times as many jobs
The Government is keen to promote Ireland as being a location where it can meet the needs of the IT sector by providing certainty around planning and power supply
Interestingly, the government is not trying to promote Ireland as a location for steel plants which would create many times more jobs. 

The impact on energy demand, fossil fuel imports, emissions, electricity prices and 2020 targets will be enormous from data centres. As a consequence, it will be harder to attract other high energy industrial users that could provide many more jobs.  There needs to be a good payback for Ireland Inc. to compensate. Of course, they need to built somewhere to provide the demand for internet services.  But Ireland should not allow so many to be built here. We simply cannot afford it. 


Approval for planning permission of any industrial project should require a high jobs to energy demand ratio of at least say six or seven. 


    

Wednesday, 29 March 2017

The Impact of High Levels of Wind Energy on Conventional Plant

On Wednesday 25th January 2017 wind energy reached a new record of 2,400MW for the Republic of Ireland. This post will look at the impacts on some of the other generation sources.


CCGT ( Gas)




Only three out of eight CCGT ran during the day - two in Dublin (Poolbeg and Dublin Bay) and one in Cork (Whitegate). Presumably, the other 5 plants were paid capacity or constraint payments to shut down for the day.

Wind generation was unusually stable during the day and so Dublin Bay and Whitegate mostly followed demand while the output from Poolbeg had a flat profile. Dublin Bay ran the most efficiently. Whitegate's output hovered between 45% and 60% of it's maximum (or rated capacity otherwise known as load). Poolbeg, on the other hand, operated at about a quarter of it's rated capacity. Operating a CCGT at this level leads to higher specific emissions and fuel consumption, something like driving your car in second gear all the time. 

It would have been therefore preferable to have operated Whitegate on higher loads and take Poolbeg off the grid altogether. The requirement for two power stations to be on load at all times in the Dublin area probably lead to this less than ideal situation.


Coal 




Two out of the the three generators at Moneypoint operated for the day and like the CCGT mostly followed demand.   They operated at an average of 50% of maximum output with minimum output at 40%. A load of 40% capacity is likewise not exactly ideal in terms of efficiency. 


Peat





The three peat power stations are being run on baseload and as a result are not affected by high wind levels. The biomass component seemed to be out of action. The question arises as to why (like wind) peat still receives a subsidy if it is always allowed to operate in the electricity generation market (Though I think the peat subsidy is being phased out). 


OCGT (Gas)




Both open gas cycle units at Sealrock operated at close to full output for the day as like wind they have priority dispatch in the system.


Demand Side Units (DSU)




One relatively new problem for Eirgrid is that despite having all this additional generating capacity in place, matching supply with demand is not as straightforward as previously thanks to the presence of stochastic wind energy. Fast acting plant is one answer to this. Another solution is reducing demand during periods of high demand. Demand side units reduce the demand during peak times giving industrial users a choice to shut down production or use their own diesel generators. 

As more wind is added, more reliance will be placed on DSUs and ironically diesel generation. During this day, on average 18MW per hour of DSU was called on to help keep the lights on. Not a significant amount at this stage. But according to Eirgrid :


The capacity of Demand Side Units in Ireland has increased to 230 MW, and is set to increase further. 


East West Interconnector to UK (EWIC)

The UK interconnector played a crucial role on this day. For most of the time, Ireland sent across it's surplus wind but for an hour, between 6pm and 7pm, Irish generation was insufficient to meet the rise in demand as people arrived home from work and turned their kettles and cookers on. It's an unfortunate fact that you can't "switch the wind on". Also you can't simply switch a large power station like a CCGT on. 

The preferred solution by Eirgrid, presumably because it was cheaper than the other option discussed below, was to reverse the direction of electricity in the interconnector. However, the UK was strapped for generation at this time and (incredibly) France were reliant on UK imports. A precarious situation for the UK but 120MW of spare power for Ireland is not a significant amount for a system of their size.




There is still a shortfall of about 200MW at peak time (where blue line is higher than orange line in the second graph above) which I'm not sure how they made up. Possibly more hydro or DSU or some other peaking plant that I may have missed.

The other option available to Eirgrid would have been to simply increase output from Poolbeg as the demand began to rise. After all, it was being operated at well below optimum efficiency as discussed above.  This is presumably what would have happened if there was no interconnector. Usually the low cost of power purchased from UK would make importing a cheaper option but I can't imagine a grid with such a tight capacity margin as the UK's giving away low cost power during peak demand times. But I can only assume it was somehow cheaper in this case.


The power UK sent to Ireland was made up mainly of gas and coal generation with some nuclear and wind : 




The generation mix for the day is given below  :




Monday, 11 April 2016

Wind Energy will provide just 3% of Peak Demand

Eirgrid expect that somewhere between 4,000MW and 5,000MW of wind will be built by 2025 :



That's enough generation capacity to almost meet projected peak demand :



However, wind energy is not normal generating capacity. A duplicate generation system will have to be maintained alongside all this subsidized wind. How much will all these new wind farms contribute to peak demand - the answer is between 3 and 4%.

That's right, Eirgrid estimate that at least 96% of peak demand will have to be met by conventional, mostly fossil fuel (presumably), sources :

All this generating capacity will require capacity payments to remain viable skyrocketing energy bills. While Eirgrid maintain that wind has some capacity credit, this ultimately proves that it has zero, which is what the Danish consider it to be (and quite rightly). You need to back up wind with 100% dispatchable generation. Which right now means either fossil fuel, nuclear or biomass. Since the Irish government are currently not in favor of the last two, that means 100% fossil fuel back up.

Source : Eirgrid, Generation Capacity Statement 2016-2025


Saturday, 19 December 2015

The Electrification Paradox

It is hard to determine exactly what the Government's long term strategy for electrification is. Like a lot of their energy policies, it is very incoherent and full of inconsistencies. Take Eirgrid's new initiative to reduce peak demand by compensating households to switch off :
EirGrid has launched a competition to identify a company who will pay householders to reduce their energy consumption at high demand times. This is one of the first times a transmission system operator (TSO) has run such a competition.  This pilot project will benefit up to 1500 householders, who will see their annual electricity bills cut by up to €100 by participating in this scheme.The competition is open to companies who will work with homeowners and EirGrid to provide a service known as “demand response”. Demand response enables electricity customers temporarily reduce their electricity consumption in response to requests from EirGrid, resulting in savings on their bills.In Ireland, businesses and industry can already do this; however, it has not been available to homeowners until now.The goal for EirGrid is to manage demand on the national grid and give homeowners more control over their electricity bills. Fintan Slye, Chief Executive, EirGrid, said: “This is a really exciting development in the electricity market. We often hear about “Smart Grids” and their benefits – this is it in reality - technology innovation that puts money back in people’s pockets.  Any measure that helps reduce overall demand on the grid, while not affecting our daily lives at work and at home, can only be a good thing in the long term.”

The reason they need to do this is because so much of our electricity is set to come from intermittent sources, mainly wind. If you have an intermittent source, then demand must also become intermittent i.e. dependent on the weather.

But the Government's Plan is to increase rail electrification in the future :

Rail electrification substantially reduces the use of fossil fuels in public transport. There has been significant progress with the introduction of DART and LUAS, and the recently published Capital Plan 2016-2021 [40] provided for further such public investment in the Greater Dublin Area. Further rail electrification will be a priority in future capital plans.
This will have the opposite effect, substantially increasing demand for electricity during peak demand times when people are leaving work. So people travelling home on an electric train will get paid not to switch on their cookers and other appliances when they arrive home. But the demand due to increased rail electrification will far outweigh the reductions from Eirgrid's demand side measures. This means that more dispatchable power stations will be required, most likely from fast acting fossil fuel sources such as gas or oil, to ensure that when a train is due to depart, it actually does so.

As noted on this blog before, no proper analysis has been done on this in terms of emissions or fuel saved. If we ran more efficient gas plants, with gradual ramping to meet gradual increases and decreases in demand, would we have more or less savings than one with a system that used wind energy and fast acting inefficient gas and oil plants as back up ?

And if you took the billions been spent on new energy infrastructure and invested that in passive houses and energy efficiency, you would most likely have a lot more savings than the current plans.

But if you don't do the calculations and allow ideology take over, as during the Celtic Tiger, then you are doomed to fail.

Tuesday, 27 October 2015

‘The Cloud’ Bytes Back - how Data Centres will cost Ireland dearly

Guest Post By David Hughes B. Arch CPMA, RIAI RIBA 


Cloud computing is now part of everyday life. From streaming services such as Spotify and Netflix to search engines and email from companies like Google and Yahoo to online storage services like DropBox… ‘The Cloud’ is both everywhere and yet seemingly invisible.

However in spite of its name, ‘The Cloud’ has some very earth bound needs and truly massive energy requirements. In fact, somewhat aptly, ‘The Cloud’ has overtaken world aviation in terms of its overall energy demand. 

These days Ireland seems to be a preferred location for the cloud’s physical footprint - data centres. These data centres will not simply serve Ireland’s data needs but the needs of all of Europe and beyond. This multiplies their energy impact on Ireland enormously and when you analyse the consequences, it is hard to see any silver lining.

To give an example Apple are seeking permission for a 240MW data centre in Athenry Co. Galway, which will create up to 215 jobs. The electricity consumption of this data centre will be the same as 420,000 Irish homes. This is ¼ of all Irish homes or every single house in Dublin City, Dun Laoghaire, Fingal and South County Dublin combined. Basically, the electricity needs of 1 Million people.

Electricity is a very expensive and capital-intensive form of energy. For every kWh coming out of a socket 2.7 kWh of Primary energy needs to be inputted at source. The transmission and distribution infrastructure or ‘grid’ is also massively expensive. This cost is ‘socialised’ and can account for 75% of a domestic electricity bill.

Cost Benefit Analysis?

As a society we may accept such costs to provide a benefit to 420,000 homes but is it really justifiable to socialise the same demand again for only 215 jobs? And Apple is only but one data centre.

Facebook’s 108MW centre will only create 40 jobs and use the energy of 180,000 homes.

In fact in total 1,000MW of data centres are projected for Ireland so on a pro rata basis will use the same energy demand as every home in Ireland.

40% Renewable Commitment.

In 2009 Ireland made a commitment to generate 40% of electricity from renewables. If we add this level of extra demand this makes that target much harder to achieve.

Last year the EPA stated that in relation to our 20:20:20 targets, we are only likely to achieve reductions of between 5% and 12% instead of the full 20% required. The SEAI calculates that the fine for this could be €1.6 Billion per annum.

The full 1,000MW of data centres could add 37% to overall electricity demand and will make our renewable targets proportionally harder to reach, the fines even higher again and last but not least will undo all of the CO2 savings to date.

In the end, trying to chase this growing demand from data centres, will spawn further Wind Farms, Pylons and Transmission lines and will leave the Irish with a second  ‘Universal Social Charge’ this time for either paying an EU fine or paying for the ‘grid’ or both.

Time for a Debate.

Given these figures it’s time for a debate on ‘The Cloud’ in Ireland. Are the numbers of jobs created in anyway justified in terms of its energy demands?

The responsibility seems to fall between a myriad of different agencies and departments pursuing different agendas but each with a focus too narrow to look at the bigger picture. As a result to date, data centres have slipped through the net unchallenged.

We are at a cross roads in terms of whether we follow a route of demand reduction or increase, however ‘The Cloud’ could create the perfect storm and sink Ireland into decades of legacy costs for very expensive and unnecessary electrical infrastructure, which could be just as painful as paying back the inflated property prices that lead to the bank bailout.


Sunday, 23 August 2015

Contribution of wind to peak demand


What was the contribution of wind to Ireland's peak demand during the most recent winter ? Remember, we are talking about over 2GW of wind capacity costing over € 4 billion to install.

The answer is very little, less than 1% :

Peak day electricity demand on the 2nd February 2015 and wind generation




Thursday, 29 January 2015

More on the Energy Bubble




Figure 1: How generating capacity has increased since 2006. East West Interconnector included in 2013 and 2014, also Great Island CCGT included in 2014 and retired oil plant on same site taken out


The above graph, Figure 1, shows the levels of electricity generation capacity for the Republic of Ireland at the end of 2014. We are now approaching the 10 GW mark, the highest ever in the State. If you really want to know why your electricity bills are so high then you only need to look no further than the above graph. All the above power stations and wind farms have to be financed through our bills, even though we only use on average less than a third, and at peak times less than half, of this capacity in electricity. The key to understanding this graph is looking at the gap between the blue (average demand) and black line (total capacity including wind) and the red (peak demand) and black line in 2006 and then comparing this gap with the current gap in 2014 (See Figure 2). As you can see, it has gone out of control. Consider that back in 2006, when the economy was booming, there were no blackouts . The level of back up capacity was sufficient but now that we have over 2GW of wind, it appears that more back up capacity is required to maintain a stable and reliable system.




2006
2014
Total Capacity
/ Average Demand
2.0 times
3.2 times
Total Capacity
/ Peak Demand
1.3 times
2.0 times
Figure 2: Total Capacity is now over 3 times that of average demand and double that of peak demand

There is an argument put forward by the Greens that this excess capacity will be required when everyone switches over to electric cars and electric heating systems as this will lead to a surge in average and peak demand. But there is a major flaw in this argument. You would still need enough dispatchable plant (i.e. plant that can be switched on and off at the touch of a button rather than when the wind blows) at least equal to the peak demand under this scenario, no matter how many wind farms there are. Otherwise, what would everyone do on a calm day like the 11th October 2014 ? Cycle the 10 or 20 miles or more to work ? Or perhaps wear extra woolly jumpers ? So you would still need to build more power stations to cover the surge in demand under this scenario and wind turbines would still result in excess capacity just like in the above graph.

Fuel Mix 2013 - another historic milestone


Figure 3: Fuel Mix 2013 with UK imports broken down into original fuel sources

Figure 3 shows that in 2013, Ireland used nuclear power for the first time. 2% of the electrons going into your electric socket in 2013 came from nuclear stations in the UK. I have broken down the power consumed here through UK imports into their energy sources and added that to the fuel mix provided by SEAI to arrive at the above chart. UK coal power accounted for 40% of our imports with gas at 25% and nuclear at 21%. The 10GW or so of UK wind provided just 6% of imports. So we are still very reliant on gas and coal power - almost 70% of the electrons entering your home in 2013 came from gas and coal power. (not including spinning reserves or back up generation)

But when we look at SEAI's original chart it tells an interesting story :

Figure 4: SEAI Fuel Mix 2013


While on the face of it, wind power did well, one has to put the output of a generator in the context of its generating capacity. The following table (Figure 5) shows the share of generating capacity each energy source had in 2013, so for example, gas plants made up 44% of the entire power plant and wind farm fleet in 2013.




Ireland's Power Generation Mix
2013
Gas
44%
Wind
20%
Coal
9.5%
Peat
4%
Interconnection
5.5%
Oil
12%
Hydro
2%
Pumped
3%
Figure 5: Generating mix 2013

Definitions used :

Grid Acceptance Rate (GAR): the rate at which when power becomes available from a generating source that it is accepted by the grid. So wind power has a grid acceptance rate of 1:1 because it has priority dispatch, meaning when wind power is available it is automatically taken by the grid. Gas has a GAR of between 1:0.8 - 0.9 because when wind becomes available it pushes gas off the grid. I will assume 1:0.85 for this analysis. Coal and Peat are assumed to have a GAR of 1:0.95 as they are occasionally pushed off by wind

Fuel / Capacity Ratio : the position of a fuel source in the fuel mix relative to its position in the generating capacity mix. So a fuel source that makes up 50% of the capacity and 50% of the fuel mix will have a fuel / capacity ratio of 1:1.

Gas power gave just over 1MW power for 1MW share of capacity so had a fuel / capacity ratio of 1:1. Peat gave over twice as much power as capacity (2:1) while coal gave approx 1.6MW power for 1MW capacity (1.6:1). It is no surprise that the highest emitting power sources produced the most power relative to their size. This is because coal and peat store higher concentrations of energy than other fuel sources having formed over millions of years. Oil power, representing 12% of capacity, had a negative fuel / capacity ratio because these plants were lying idle most of the time. Oil plant are mostly used for "peaking" , i.e. when peak demand goes above normal which doesn't happen very often nowadays. So it had a significantly low Grid Acceptance Rate (somewhere around 1:0.01), whereas gas, peat and coal had GARs very close to 1:1 (between 1:0.85-0.95)


So how did wind do? Well, it had a negative output relative to its share of capacity. It comes out at 0.8MW of power for each share of MW installed. This is despite it having priority dispatch i.e. when the wind blows, the power is taken straight away by the grid. So levels of other power sources - mostly gas, and sometimes coal and peat - are reduced when wind is available. Applying the above definitions, this means that wind had the best Grid Acceptance Rate of all fuel sources i.e 1:1, but had a negative fuel / capacity ratio of 0.8:1. So wind and oil came out the worst, but oil had the lowest Grid Acceptance Rate, whereas wind had the highest. What this shows is that wind is a poor storage of energy when compared to coal, gas, peat and oil and storage solutions cannot solve this problem, rather it simply transfers the storage of this energy from one hour to another. What is required is a renewable source that contains higher concentrations of energy


And herein lies the problem with wind energy - you can't run a reliable grid if you install power plants that almost always give a negative fuel / capacity ratio. If you install 1,000 MW of wind, and demand hits 1,000MW, the power from the wind will almost always be less than 1,000MW so you have a blackout. This problem means that wind energy can never replace conventional plant and so competitiveness goes out the window