Monday, 12 March 2018

Interconnector Fault Causes Problems for Wind Farms During Beast from the East


As the "Beast from the East" hit Ireland on the 28th February, things were looking good for wind farmers. The east winds were predictable and constant, unlike the variable westerlies that hit Ireland most of the time. Wind energy became baseload power for the first time on the Irish grid. On the 1st March, the capacity factor for wind was 80%, a power output normally reserved for coal or gas generation. However, a problem occurred on the morning of the 28th. The interconnector to the UK (East West interconnector) tripped out. This meant that surplus wind generation could no longer be exported to the UK. High amounts of wind generation would have to switched off or "curtailed".


Wind generation and forecasted wind during Beast from the East. Note how accurate the forecast was
with one notable exception (see later)

East West interconnector fault on 28th February


A further problem happened on the 2nd March as the storm reached it's peak. Power cuts became a frequent event. Power cuts are inevitable of course during storms and periods of extremely high winds, which is very unfortunate for wind farmers as demand for their product, electricity, is reduced just when their supply is at it's highest. In fact, over the four or five days of the "Beast", demand was relatively normal. This is in stark contrast to the Big Freeze event of 2010 where demand reached over 5,000MW (and wind generation was abnormally low). During the Beast, demand reached a high of about 4,600MW on the 28th February. The periods of highest winds (1st - 3rd march) saw demand reach only 4,200MW.


Demand all time peak 2010 Vs Demand during Beast from the East 2018

Power cuts on the 2nd March

 On 1st March, wind energy was generating about 59% of the total electricity production, one of the highest penetrations ever. However, by the next day, as power cuts became widespread, wind energy was been curtailed by as much as 45%. Nearly 1,200MW of wind was been shut down at 4am. 

The period from 1st to 2nd March was when the storm was at it's most intense in Ireland. 
Wind curtailment can therefore be calculated as the difference between forecast wind and actual wind. 
Forecast wind generation was actually equal to demand at times.
The frequency of electricity, normally static at 50Hz, became erratic during the storm as the grid
operator struggled to manage high wind penetrations. This is from the 2nd March.

Had the interconnector been in operation, 500MW of this surplus wind could have been exported.  Demand, in fact, dropped by 10% on the 2nd March compared with the day before, presumably due to the power cuts. 

These are problems that will only intensify as more wind capacity is added and more and more generators are looking to get a piece of the demand "pie". Interconnectors, like storage, seem like an easy solution in theory, but in practice things are often different. 




6 comments:

  1. So you can expect a nation wide grid collapse any day now. Courtesy of the averages people from Eirgrid and the Regulator. Buy in a good supply of tinned food.A gas stove would also be handy. Plus a couple of pots to boil the water for a cup of tea, cook the bacon , etc.

    ReplyDelete
  2. They appear to have overestimated demand which was reduced by interconnector failure. In the past 2 weeks, wind have varied massively, but today it @ 60%. A serious inhibitor in monitoring it is the constant breakdown in Eirgrid's dash board reports. It occurs only during high winds and leads to suspicion of rigging. Why can't they publish as it happens. If you use the dashboard, it is simpler to use Ireland only. The question might be asked, what is happening to conventional plant while wind is coming in? They obviously have to be kept viable by a favorable subsidy.

    ReplyDelete
    Replies
    1. It would be more accurate for Eirgrid to publish what conventional plant is running behind the wind. And what demand side units are been used to reduce demand. The current dashboard does not give a complete picture of whats actually going on.

      Delete
  3. So what is that EWIC fault .. how long will it last .. who caused it and why do they trip every few months .. how much is lost .. will they build another one?

    ReplyDelete
  4. After the strong performance of Ireland's wind farms yesterday when they were achieving over 60% penetration, I had hoped to check the Dashboard this morning to see how much output dropped off. Winds are noticeable weaker now and that would beg the question of how much conventional plant is being kept running to take up the slack? In a worst case scenario, wind could be acting as a side car to a fossil fuel propelled motor cycle. Whether the co2 emissions from such plant is measured, no one knows. We may be getting propaganda, not facts. Eirgrid should have a spokesperson to deal with public queries. A press officer, in the same way that the Garda Siochana have one.

    ReplyDelete
  5. Will they build another EWIC ?. Hardly likely the last one cost €650m. We paid 100%. The Brits did not spend a penny. We are exporting most of the electricity at negative prices. In other words we pay the Brits to haul the waste away. Clever ain’t it.

    ReplyDelete