Showing posts with label interconnection. Show all posts
Showing posts with label interconnection. Show all posts

Wednesday, 24 November 2021

Peak Winter Demand Arrives

Things get a little bit shaky !

 Last night at 5.30pm, the electricity grid hit peak demand for All Ireland at 6,638MW - not far off Record peak demand of 6,878MW reached on December 21st last year.



.

But total system generation was only 6,106MW leaving a shortfall of 532MW.  


Wind energy was low most of the day, only 380MW or about 7% was available for the whole island at 5.30pm.



The two UK interconnectors saved the day with combined imports of 450MW. There was still a shortfall of about 80MW, made up presumably from demand side units. These would comprise mostly of diesel generators and combined heat and power units. These units are "non-centrally monitored" according to Eirgrid and are not included in these graphs.  



Of course, that damned Brexit lot across the sea with their dastardly nuclear power charged us handsomely for the imported power, at € 2,000 a MW. 




To give some credit to the Irish grid operators, they were correct to build the East West interconnector as it is making up for the once efficient gas plant that have been prematurely wrecked from backing up the wind. One just hopes that the UK will have sufficient power to give us on those cold winter nights over the next few months. 






Tuesday, 10 March 2020

Does Wind Energy Reduce CO2 Emissions ?

There has been a lot of coverage recently about how much wind energy is contributing to the electricity grid, but how much CO2 is it really saving ?

The graphs below, based on data from eirgrid dashboard, show that on some days there is absolutely no savings at all.

The two days being compared are 23rd January 2020 and 29th of November 2019. Note that wind generation (blue) on 29th November is over 7 times that of 23rd January 2020 but CO2 emissions (in yellow) are virtually identical.





East West interconnector (in green) minus figures are exports, pluses are imports. At 329 grams CO2 on both days EWIC imports are very close 84 and 81 MW on the 23rd January 2020 and 76 and 1 MW 29th of November 2019 (circled). However, even though wind output is over 5 times higher on the 29th November, CO2 emissions remain static at 329. 

This raises serious questions about the effectiveness of wind energy in the irish grid. 

Thanks to John Dooley for providing the graphs. 

Wednesday, 26 December 2018

Ireland Exporting Fossil Fuel Power


According to Eirgrid's East West Interconnector brochure, one of the benefits of the interconnector to UK is that it "facilitates growth in renewable energy".  What is not often mentioned is that sometimes we in Ireland are actually exporting fossil fuel power through the interconnector. During the recent summer, when there was little or no wind, the interconnector was doing just this most of the time -  exporting fossil fuel electricity generated in Ireland to the UK :
The period of low wind this summer




https://www.gridwatch.templar.co.uk/


Because of EU emission rules, the carbon emissions for these exports will be counted in Ireland, the country of origin, which will benefit UK with emission free electricity. 






Saturday, 3 November 2018

Only Ten Percent of Wind Capacity can be Relied Upon Over Winter

Eirgrid, the grid operator, have assessed that only 10% of the entire wind generation fleet in Ireland can be relied upon during the high electricity demand winter period. Solar power fares even worse as zero solar capacity can be relied on as the dark cold evenings draw in.


Conventional gas and coal generators are considered to be around 90% reliable as they can be switched on and off when called upon, once sufficient notice has been given. However, wind is unreliable in nature and is therefore given a "capacity credit" to take account of this unreliability :


 Given the variable nature of wind power, the wind capacity credit expresses how much conventional power generation can be avoided or replaced by a certain level of wind power. 

Only 476MW out of a total of 4,617MW or about 10% can be relied upon in the event that a conventional generator fails :


When it comes to keeping the lights on there is no room for the hyperbole and feel good talk that permeates much of the debate around renewables in the media and in the chambers of the Irish parliament.

The spare generating capacity above electricity demand is called the capacity margin. It has halved from 3,199MW in 2016 to 1,793MW in 2018. Two gas powered generators have closed down in 2018 and Moneypoint coal power station has suffered an outage. 



Generators shut down
Output MW
Aghada AD1 (gas fired steam turbine)
258MW
Marina (open cycle gas turbine)
95MW
Moneypoint (coal)
855MW

1,208MW


In recent days, it was gas power, the UK interconnector and "other" generators (presumably peat and oil) that ensured the lights stayed on in the absence of Moneypoint and the above units. Renewables (mostly wind energy) varied between 7% and 27% so could not be depended on. Back up power stations are still essential in a grid with large amounts of renewables.











You can also see the importance of the interconnector with the UK (EWIC). Can the UK guarantee they will have spare capacity to export electricity to Ireland ? The black line below shows the profile for coal power in the UK in recent days. As you can see, they too were having problems with their coal units.


Scotland too is in a precarious position and will likely be reliant on imports from the UK over the winter period :

At the time of writing the Torness 2 and Hunterston 3 and 4 reactors were down, leaving Scotland with only 612 MW of nuclear capacity and only 3,900 MW of dispatchable capacity to service over 4,000 MW of demand. However, all three reactors are scheduled to restart by mid-December, and any shortfalls that might occur in the meantime could probably be covered by imports from England [Euan Mearns]

If we get a very cold winter, and there are indications that a cold one is coming, the already strained grid could come under a lot of pressure as demand increases. Couple this with more generator outages, and we could be in for some big problems. This is where the demand side of the equation would become crucial - essentially disconnecting large energy users from the grid who would have to rely on their own generation i.e. diesel generators or combined heat and power. 

Essentially, a return to the pre grid times of the early 1900s, when there was a large and inefficient diesel generator in most big towns in Ireland. 

Monday, 12 March 2018

Interconnector Fault Causes Problems for Wind Farms During Beast from the East


As the "Beast from the East" hit Ireland on the 28th February, things were looking good for wind farmers. The east winds were predictable and constant, unlike the variable westerlies that hit Ireland most of the time. Wind energy became baseload power for the first time on the Irish grid. On the 1st March, the capacity factor for wind was 80%, a power output normally reserved for coal or gas generation. However, a problem occurred on the morning of the 28th. The interconnector to the UK (East West interconnector) tripped out. This meant that surplus wind generation could no longer be exported to the UK. High amounts of wind generation would have to switched off or "curtailed".


Wind generation and forecasted wind during Beast from the East. Note how accurate the forecast was
with one notable exception (see later)

East West interconnector fault on 28th February


A further problem happened on the 2nd March as the storm reached it's peak. Power cuts became a frequent event. Power cuts are inevitable of course during storms and periods of extremely high winds, which is very unfortunate for wind farmers as demand for their product, electricity, is reduced just when their supply is at it's highest. In fact, over the four or five days of the "Beast", demand was relatively normal. This is in stark contrast to the Big Freeze event of 2010 where demand reached over 5,000MW (and wind generation was abnormally low). During the Beast, demand reached a high of about 4,600MW on the 28th February. The periods of highest winds (1st - 3rd march) saw demand reach only 4,200MW.


Demand all time peak 2010 Vs Demand during Beast from the East 2018

Power cuts on the 2nd March

 On 1st March, wind energy was generating about 59% of the total electricity production, one of the highest penetrations ever. However, by the next day, as power cuts became widespread, wind energy was been curtailed by as much as 45%. Nearly 1,200MW of wind was been shut down at 4am. 

The period from 1st to 2nd March was when the storm was at it's most intense in Ireland. 
Wind curtailment can therefore be calculated as the difference between forecast wind and actual wind. 
Forecast wind generation was actually equal to demand at times.
The frequency of electricity, normally static at 50Hz, became erratic during the storm as the grid
operator struggled to manage high wind penetrations. This is from the 2nd March.

Had the interconnector been in operation, 500MW of this surplus wind could have been exported.  Demand, in fact, dropped by 10% on the 2nd March compared with the day before, presumably due to the power cuts. 

These are problems that will only intensify as more wind capacity is added and more and more generators are looking to get a piece of the demand "pie". Interconnectors, like storage, seem like an easy solution in theory, but in practice things are often different. 




Wednesday, 29 March 2017

The Impact of High Levels of Wind Energy on Conventional Plant

On Wednesday 25th January 2017 wind energy reached a new record of 2,400MW for the Republic of Ireland. This post will look at the impacts on some of the other generation sources.


CCGT ( Gas)




Only three out of eight CCGT ran during the day - two in Dublin (Poolbeg and Dublin Bay) and one in Cork (Whitegate). Presumably, the other 5 plants were paid capacity or constraint payments to shut down for the day.

Wind generation was unusually stable during the day and so Dublin Bay and Whitegate mostly followed demand while the output from Poolbeg had a flat profile. Dublin Bay ran the most efficiently. Whitegate's output hovered between 45% and 60% of it's maximum (or rated capacity otherwise known as load). Poolbeg, on the other hand, operated at about a quarter of it's rated capacity. Operating a CCGT at this level leads to higher specific emissions and fuel consumption, something like driving your car in second gear all the time. 

It would have been therefore preferable to have operated Whitegate on higher loads and take Poolbeg off the grid altogether. The requirement for two power stations to be on load at all times in the Dublin area probably lead to this less than ideal situation.


Coal 




Two out of the the three generators at Moneypoint operated for the day and like the CCGT mostly followed demand.   They operated at an average of 50% of maximum output with minimum output at 40%. A load of 40% capacity is likewise not exactly ideal in terms of efficiency. 


Peat





The three peat power stations are being run on baseload and as a result are not affected by high wind levels. The biomass component seemed to be out of action. The question arises as to why (like wind) peat still receives a subsidy if it is always allowed to operate in the electricity generation market (Though I think the peat subsidy is being phased out). 


OCGT (Gas)




Both open gas cycle units at Sealrock operated at close to full output for the day as like wind they have priority dispatch in the system.


Demand Side Units (DSU)




One relatively new problem for Eirgrid is that despite having all this additional generating capacity in place, matching supply with demand is not as straightforward as previously thanks to the presence of stochastic wind energy. Fast acting plant is one answer to this. Another solution is reducing demand during periods of high demand. Demand side units reduce the demand during peak times giving industrial users a choice to shut down production or use their own diesel generators. 

As more wind is added, more reliance will be placed on DSUs and ironically diesel generation. During this day, on average 18MW per hour of DSU was called on to help keep the lights on. Not a significant amount at this stage. But according to Eirgrid :


The capacity of Demand Side Units in Ireland has increased to 230 MW, and is set to increase further. 


East West Interconnector to UK (EWIC)

The UK interconnector played a crucial role on this day. For most of the time, Ireland sent across it's surplus wind but for an hour, between 6pm and 7pm, Irish generation was insufficient to meet the rise in demand as people arrived home from work and turned their kettles and cookers on. It's an unfortunate fact that you can't "switch the wind on". Also you can't simply switch a large power station like a CCGT on. 

The preferred solution by Eirgrid, presumably because it was cheaper than the other option discussed below, was to reverse the direction of electricity in the interconnector. However, the UK was strapped for generation at this time and (incredibly) France were reliant on UK imports. A precarious situation for the UK but 120MW of spare power for Ireland is not a significant amount for a system of their size.




There is still a shortfall of about 200MW at peak time (where blue line is higher than orange line in the second graph above) which I'm not sure how they made up. Possibly more hydro or DSU or some other peaking plant that I may have missed.

The other option available to Eirgrid would have been to simply increase output from Poolbeg as the demand began to rise. After all, it was being operated at well below optimum efficiency as discussed above.  This is presumably what would have happened if there was no interconnector. Usually the low cost of power purchased from UK would make importing a cheaper option but I can't imagine a grid with such a tight capacity margin as the UK's giving away low cost power during peak demand times. But I can only assume it was somehow cheaper in this case.


The power UK sent to Ireland was made up mainly of gas and coal generation with some nuclear and wind : 




The generation mix for the day is given below  :




Monday, 20 February 2017

The French - Irish Interconnector



Pat Swords on the proposed Interconnector from Ireland to France :

JP Morgan famously said: “A man has two reasons, the good reason and the real reason”. Thought about that today when I saw the latest spin from Eirgrid, i.e. spending €1 billion of our money, which was of course for our wonderful benefit:
One has to laugh at the total ignorance of the press, do they ever actually think about the crap they write, although if we had to pay to read it like in the past, nobody really would anymore.
This €1 billion interconnector to France is to power 450,000 homes and increase security of supply, which is a bit daft, as we already have a system, which does that and has been ultra reliable for decades, so why do we need to spend another €1 billion on another one to do the same thing?
Yes France has a lot of cost competitive nuclear, but when the cold weather hits France, their electricity consumption soars, as they have a lot of domestic electric heating. If you don’t believe me watch the dial on the top left when the cold weather comes in, they are really struggling to match demand during these periods

http://www.gridwatch.templar.co.uk/france/
When the cold weather hits France it often hits here too. So if we bring in French nuclear off peak and at competitive prices, this is a short term gain, but means that some of our existing generation capacity will simply in time shut up shop. So what happens then when it gets real cold? Of course the French will suffer blackouts, as the lovely new interconnector keeps sending French electricity to Ireland. After all there is plenty of precedent of such issues and how we can rely on the EU’s trading ‘rules’ when the ‘chips are down’:
Maybe people will smell the coffee when the power eventually comes back on and they can brew it?
So let’s get down to the real reason, which one will never get from the so called professionally paid news media. One has to ferret it out oneself, such as using the Aarhus information rights utilised effectively in the article above. However, isn’t it amazing how our so called ‘public servants’ (don’t make me laugh), try every trick in the book to obstruct citizens seeking information, even to the point of breaking the laws, which apply to them?
With regard to this wonderful interconnector, it is part of the EU’s Projects of Common Interest, which has been part of a long drawn out Communication at UNECE, which is in its final phase with the draft findings and recommendations likely to be out this spring. The EU fought tooth and nail, right to the head civil servant in the EU Catherine Day (wouldn’t you know it Irish!), that nobody would have access to information relating to the justification for these projects. However, go to Annex 6 of the Communication and Questionnaire for E 153 – Grid Link (page 83/119 of the pdf)
“This investment is planned primarily to facilitate the integration of 1,283 MW of wind generation in the south of the country. This is approximately equivalent to 0,054 GW/1000 km2 based on GW of additional wind installed within county boundaries. Because of the favourable wind conditions on the island of Ireland and offshore there is interest (evidenced by applications for grid connections) in developing renewable generation capacity well in excess of what is required for native demands. The connection of such capacity can only be facilitated if further interconnection is installed to provide access for this generation to the British and continental European markets, in addition it will facilitate future interconnection to Great Britain or France.”
One of the things that is strikingly clear, is that the Irish grid system can’t take more wind without a major build-out, which includes more interconnectors. So developers may well get their planning for wind turbines, but the realty of project completion and operation hinges on other developments in grid infrastructure, including those interconnectors. The East West interconnector, linking Malahide to the Welsh grid, cost Irish consumers over €600 million and the UK consumers not a cent. It was raised, but not addressed in the first Communication I brought in 2010 to UNECE.
For instance, the below from what is a ‘Green tinged (and funded) German think Tank’:
Social cost benefit analysis of interconnector investment: A critical appraisal
Bremen Energy Working Paper No. 02, July 2010 (published in Energy Policy, 39(6), 2011, pp. 3096-3105.) Michiel de Nooij
Abstract
“Some, like the European commission, claim that Europe needs more transmission capacity and interconnectors. This paper studies interconnector investment decisions from the perspective of a social cost benefit analysis (maximising total welfare in a country). For two European decisions to build an interconnector (NorNed and the East West Interconnector) the analysis underlying the decisions is discussed in detail, and will be compared with lessons from theory and decisions made in other jurisdictions (Nordel, California and Australia). The key findings are that (i) it is unclear how much demand for transmission capacity and interconnectors there actually is, and thus how large the benefits of investing will be. (ii) Both studies analyzed are not correct. Main criticism includes that they do not take the reaction of producers to new interconnection capacity into account; ignore part of the potential benefits of more competition; and make a strange assumption with respect to discounting. (iii) Decisions in Europe are taken very differently, leading to situations in which approval of an investment might depend on who has to approve. (iv) Therefore, it is unlikely that interconnector and transmission investment decisions in Europe currently are maximizing social welfare. Some lessons for future cost benefit analysis are drawn.”
In other words, the figures were a fudge and there was no rational economic justification for it, it all came down to ‘who has to approve’!
This same point came up with the Irish Academy of Engineering’s report in 2009:
“1.2.3 East­West Interconnection (EWIC), In July 2006, the Irish Government decided to construct an interconnector from Ireland to Great Britain. It would appear that this decision was taken without the benefit of a robust techno‐economic study or cost benefit analysis.  
In addition it is not clear that the main benefit, the “capacity savings”, amounting to some €40m annually out of a total annual benefit of €66m, would be attainable under current market rules, as the benefit would appear to imply 100% usage of the interconnector. The Academy understands for example that during 2008 the usage factor on the Moyle interconnector was approximately 14%. This would appear to indicate a much lower likely benefit from EWIC.”
Looks like Eirgrid are happy to dismiss these issues for their projects on the basis that the punters and decision makers (a shower of punters with our money) only read the crap in the Irish Independent, etc., which is a reproduction of what they feed the lazy journos in the first place.
God help us from all this stupidity and the appalling mess it leaves behind, as if we didn’t have A&Es and hospitals crying out for investment, etc.



French Grid Case Study - 20th January 2017

Figure 1
Figure 2



On 20th Jan, as demand hit 93.8GW (Figure 2), France was dependent on over 4.5GW of imports (Figure 1). In previous years, France was a net exporter. At the same time in Ireland, wind was only at 30% of max output leaving nothing for export if an interconnector to France was in place. Most likely French grid operators were engaging in load shedding to prevent blackouts - see here for more details 

Thursday, 22 September 2016

Rise in Ireland's Electricity Generation CO2 Emissions


SEAI have published the latest details on CO2 emissions in Ireland. Electricity generation emissions have risen in 2015 because of a rise in coal consumed in Moneypoint.




The graph is slightly misleading for a couple of reasons. It uses a simplified modelling system that doesn't take full account of increased cycling and ramping from back up generators. Hence the disclaimer on Page 26 :


There are clear limitations in this analysis but it does provide useful indicative results. 

The cycling effects are certainly not small as stated on Page 21 - see here for an analysis

http://euanmearns.com/co2-emissions-variations-in-ccgts-used-to-balance-wind-in-ireland/


In reality, the cycling effects increase as more wind is added so the CO2 per kWh of electricity may be fairly accurate back in say 2010 but starts getting progressively worse by 2015. 

The other problem is that by the end of 2012, the East West Interconnector was up and running sending Co2 free power to Ireland throughout 2013 and after that. This is because emissions are counted in the country of origin, in this case the UK. No account seems to be taken in the graph above of this. There is no Imports (avoided) in the legend.

Lastly, as stated recently on this blog, use of diesel generators is becoming more common with increased intermittent wind power, and is now at about 230MW capacity. I can't find any reference to them in the SEAI paper so presumably they are not included. 

Thursday, 18 August 2016

Will The Lights Stay on in Ireland ?


A new report by the European Network of Grid Operators (ENTSOE) has shown that Great Britain may not have sufficient electricity generation capacity by 2020 to keep the lights on. This has a knock on affect here in Ireland where by 2022 it is envisaged that we will become more and more dependent on interconnectors.

ENTSOE have placed Britain at the highest risk level of grid blackouts in EU but state that expensive Capacity Mechanisms may prevent them from happening. For the layman reading, this is due to lack of investment in baseload generation - gas, coal, nuclear. Lack of sufficient baseload generation in UK means interconnectors to Ireland will lie idle (where Ireland is also strapped for reliable means of power to export to UK). 

Eirgrid this year published their generation adequacy assessments up till 2025




Take a look at the bottom section which excludes interconnection. Green means we have sufficient generation, red means we don't. By 2022, things start getting tight, by 2023 and 2014 we are in blackout territory, highly dependent on UK to send us spare power. 

Of course, we have spent billions on new wind farms. But as ENTSEO state :
The contribution of RES [renewables] for adequacy purposes is less than for thermal plant.

I've dealt with this concept before - capacity credit.  Wind farms don't keep the lights on, power stations do. 

There is a further problem for the Irish Grid operators - Eirgrid - and that is the new data centres that are been built around the country. They consume lots of power - Eirgrid estimate that if all the data centres that are contracted are built, they will add a whopping 1,700MW on top of peak demand of about 5,000MW. This would mean we get into the red a lot quicker. 

There is a quick fix to this, of sorts, and I hinted at it earlier - Capacity Mechanisms. This involves load shedding - paying factories large amounts of money to close for a period and / or diesel generation which can ramp up alot quicker than power stations. Ireland had about 60MW of diesel generation in 2014 (referred to as Demand Side Units), we now have 230MW ! And Eirgrid have said :


The capacity of Demand Side Units in Ireland has increased to 230 MW, and is set to increase further. 

How ironic that the green revolution, the de-carbonization of our grid, the clean, green future has lead to us using more and more diesel generation - the most polluting form of electricity production. And of course, our neighbours England are also going down this path. 

Incidentally, the data centres will have back up power in the event of widespread blackouts. No, not windmills, yes you guessed it - diesel generators. The new Apple data centre in Galway will have 18 generators with a total capacity of 288MW. The new green revolution is upon us !

Tuesday, 2 February 2016

Who pays for the North South Interconnector and why?


Guest post by Pat Swords. 

Is the North South Interconnector worth the investment, who pays and who benefits ?  

The amount of money we are paying in our electricity bills for grid expansions and the lack of reasons why, is starting to reach epidemic proportions. The recent Energy Green Paper in its Figure 5 shows the breakdown of the domestic electricity rate, in which transmission and distribution, i.e. the grid, amount to some 34% of the domestic electricity price (an additional VAT at 13.5% is then applied).

So we can deduce that nearly a third of what we pay on our final bill is going to fund the grid. As such then, one should be highly concerned, when in 2011 Newspaper articles entitled "Ireland's big hope or just hot air" are published. These summarise the position of the Irish Academy of Engineering with respect to the proposed roll out of the renewable energy programme and supporting grid infrastructure.

As the article highlights:
  • Between now and 2015, billpayers will also pay at least €1.4 billion in grid development and improvement costs that are necessary for the development of more wind farms, according to grid operator Eirgrid.
  • In addition, there is the €500 million cost to billpayers of the East-West interconnector, also needed to facilitate more wind energy, it says.
  • Another aspect of all this, perhaps indicating the true total cost of all of this wind energy, is that the ESB in 2008 announced plans to invest €11 billion in the grid and a further €11 billion in renewables and smart meters by 2020, although ESB sources say this strategy may be revised. 

Therefore, we are looking at potentially some €13 billion to be spent on the grid, both for high voltage (Eirgrid) and medium voltage (ESB), in order to facilitate all of this renewable programme. This is a staggering amount of money. Indeed to put it in its context, if we go back to Figure 5 in the Green paper, some 46% of the domestic rate is the wholesale price and 80% of that is fuel for the power stations. In other words, a third of what you pay in your final bill is fuel for the power stations. Yet it can quite easily be calculated, that if there was no wind energy, Irish thermal power stations could be kept running for a fuel cost amounting to some €1 billion per year. 

If one was to use simple maths and ignore such issues as that some electricity is sold at a lower rate to industry, one gets the simple answer, in that if we didn't progress all this grid expansion to facilitate renewables, we could have free electricity instead for four years. Note: This is not an unreasonable conclusion, there is no such thing as a 'free lunch' and all these billions for investment in renewable infrastructure has to come out of unnecessarily soaring electricity bills.

So let's examine the roll out of the North South Interconnector and particularly what's in it for us the consumer in the Republic of Ireland. Why should we be paying for this 400 kV line running 103 km through the Republic and a further 34 km through N. Ireland? In essence, it doesn't take a genius to figure out, that as more three quarters of the infrastructure lies in the Republic, we are the ones with the biggest cost exposure. As to what this cost exposure actually is can be seen in the European Platform Against Wind Farms (EPAW) submission on the North South Interconnector:


As Section 6.6 of this clarifies; Jenny Pyper, who is the Chief Executive of the Utility Regulator in Northern Ireland, stated to the Oireachtas Committee on the 16th June 2015:


  • I should apologise for the absence of a crucial bullet point which provides the total project cost of the North-South interconnector, including overhead line, land acquisition, substation and other costs. The total project cost is €286 million

  • It is important to understand that, while the security of supply concerns do not directly apply to us - we probably have more comfort in the Republic in terms of the capacity available for generation - there is an argument that we have an excess that cannot flow to Northern Ireland because the second interconnector is not available at the moment, which is imposing costs on consumers. This extra cost, which we think at minimum is about €10 million per annum, is the primary concern from the Republic's point of view.

So let's think this through; the Republic of Ireland doesn't need to import any power from Northern Ireland, as it has a surplus of generation capacity. Jenny Pyper is claiming that the presence of the interconnector would lead to greater efficiencies in thermal power plant generation, which would amount to some €10 million per annum. This is complete peanuts in an all island electricity market, which pays each year some €2.75 billion to generators, to which grid costs, etc.have to be added before the final consumer price is arrived at. Furthermore, it is generally recognised that the economic lifespan of high voltage transmission systems is 45 to 50 years, so the simple payback on this proposed North South Interconnector project would be in the order of half its expected lifespan. In engineering terms this is simply absurd.

So why are we doing this, when clearly the bulk of the economic and environmental costs are to be picked up by the consumers in the Republic of Ireland, who have absolutely no need for this investment? 

It doesn't take long to figure out that all of this investment is for the 'Glory' of even more renewables. As Section 4.1 of the EPAW document shows:

  • The governments of Ireland and Northern Ireland have both set targets of meeting 40% of electricity consumption from renewable sources by 2020. This is expected to be achieved mainly by significant amount of new wind generation capacity in both jurisdictions. The RIDP project is required to facilitate the connection of wind generation in Donegal in Ireland and in the west and north of Northern Ireland, where the renewable resources are largely located. The additional grid transfer capacity provided by this North South 400 kV interconnection project is essential to allow access to a larger market for the new renewable generation, particularly for Northern Ireland wind generation in times of high wind conditions and low local demand. This project therefore indirectly allows the connection of 600 MW in Northern Ireland, i.e. the equivalent of the additional grid transfer capacity initially provided by the link.

So what does this mean in real terms? Well first of all the power generation situation in N. Ireland is in a complete crises, as nobody will invest in the conventional generation necessary to keep the lights on. This is described in detail in Sections 5.2 and 5.3 of the EPAW document, but in simple terms why would one put hard earned cash into a conventional generation plant there, when the market place is to be turned over to the new renewable generators and the power stations in the Republic of Ireland. The latter to have improved access through the capacity of this new interconnector. The whole thing is actually quite nasty, Government funded renewables and interconnectors are putting conventional plants out of business in N. Ireland and the fact that there are no longer sufficient conventional generators left in N. Ireland is then being used as the justification for those same projects. Yet if those State sponsored schemes weren't there, there would be plenty of companies interested in the N. Ireland power generation market. 

In fact you couldn't make it up, consumers in the Republic of Ireland are now to finance ill-conceived interconnector projects, which would never happen without massive subsidies, while the alternative makes absolute 100% sense. Finance nothing and let N. Ireland have a proper vibrant electricity market, in which its own electricity consumers finance the necessary convention power generation it requires. Not only is this proper economics and provides the security of supply that N. Ireland requires, but it prevents the completely unnecessary scarring of the Irish countryside with over 137 km of massive pylons, associated medium voltage transmission lines and more than 300 additional wind turbines in N. Ireland alone.