Things get a little bit shaky !
Last night at 5.30pm, the electricity grid hit peak demand for All Ireland at 6,638MW - not far off Record peak demand of 6,878MW reached on December 21st last year.
But total system generation was only 6,106MW leaving a shortfall of 532MW.
Wind energy was low most of the day, only 380MW or about 7% was available for the whole island at 5.30pm.
The two UK interconnectors saved the day with combined imports of 450MW. There was still a shortfall of about 80MW, made up presumably from demand side units. These would comprise mostly of diesel generators and combined heat and power units. These units are "non-centrally monitored" according to Eirgrid and are not included in these graphs.